CMHC Memo: Week of Jun 28

28 Jun 2021 9:03 AM | Anonymous

For the most up-to-date info please visit: admin.granvilleisland.com or email Tenant Coordinators at coordinators[at]granvilleisland.com


 Sandblasting

This work will continue as in previous weeks, from Monday to Friday (7AM to 5PM) and Saturday/Sunday (7AM to 3PM), weather dependent. Please note that CoV's contractor has obtained a Noise Exception Permit in order to expedite construction and project completion. There may be sandblasting noise from 8PM to 10PM, starting next week until Monday, July 5th.

Scaffolding Removal

CoV will be implementing a new exclusion zone in the Chain & Forge parking lot, as shown below, to facilitate the removal of scaffolding from under the bridge.